Drill Pipe Discharge — Crane Simulation

Bird's-eye view of one hold being discharged. Single crane vs two-crane pre-slinging. Set one round-time per crane and watch it play.

Settings

×
pc
s
s

Tip: with 1 crane the same crane does the pre-slinging itself, so the two times run one after another. With 2 cranes they run at the same time — you go as fast as the slower crane.

Economics (optional)

$
$

Bird's-eye view

Speed 24×
Mode: 2 cranes Lifts landed: 0 / 60 Sim clock: 0m 00s Est. total this hold:

Result

1 crane — total
2 cranes — total
Time saved
Throughput 2-crane
lifts / hour
1-crane cycle / lift
2-crane cycle / lift
Crane 1 utilisation (2-crane)
Crane 2 utilisation (2-crane)
How the model works

One crane: the crane does the pre-slinging itself and then the lift, one after the other → time per lift = Crane 1 + Crane 2.

Two cranes: Crane 2 pre-slings the next bundle while Crane 1 is delivering the current one, so they overlap → time per lift = max(Crane 1, Crane 2). You go as fast as the slower crane. If Crane 2 is slower than Crane 1, it sets the pace (bottleneck).

Total = time per lift × number of lifts. Times are your own round-time estimates for each crane; tune them to your gang and vessel.

Operational planning model for C. Steinweg — figures are only as good as the two round-times you enter.